- Contract signature: 25/11/2010
- OS start of work: 20/12/2010
- Contract Completion: 04/12/2013
- End of updated work taking account of the amendment: 01/28/2016
- Contractual period updated: 1865 days
- Contract Amount: 16 260 851.468 DT TTC
The overall progress of studies and execution of the order of 94%.
Lot 4 : STATIONS | TYPE | % Avancement des études |
---|---|---|
ENNAJAH | SS + RDC | 95% |
ETTAYARANE | SS + RDC | 90% |
EZZOUHOUR | SS + RDC | 100% |
HRAIRIA | SS + RDC + 1 ET | 87% |
BOUGATFA | SS + RDC + 1 ET | 98% |
The overall physical progress is about 69%.
Lot 3 : STATIONS | TYPE | % Avancement des travaux |
---|---|---|
ENNAJAH | SS + RDC | 59% |
ETTAYARANE | SS + RDC | 61% |
EZZOUHOUR | SS + RDC | 66% |
HRAIRIA | SS + RDC + 1 ET | 61% |
BOUGATFA | SS + RDC + 1 ET | 82% |
- Ennajah Station: Transplanting, metalwork, painting and plumbing;
- Tayarane Station: slab formwork Shelters 1G and 1D, installation of wrought iron door, Hall traveler painting, plumbing;
- Ezzouhour Station 2: Façade jackets Structured concrete coatings desk, iron door installation, plumbing works;
- Hrairia Station: staircase cladding, coating basement, wall covering, coated in Shelter B ceiling, waterproofing, wood carpentry joined administration, wrought iron windows, sanitary wall coverings floor seal 2, elevator seal 4, poses frame staff , transplanting;
- Bougatfa Station: Wall coverings basement, aluminum joinery, metalwork, decorative tube installation, Hall traveler paint, plaster ceilings Shelter, casing, plumbing.
- Ennajah Station: casing basement administrative block painting, structured concrete;
- Ettayarane Station: wrought iron, tile shelters 1G and 1D, painting;
- Ezzouhour Station 2: Structured coatings for concrete facades, aluminum carpentry, Hall traveler painting;
- Hrairia Station (O 2): Works fake ceiling, wall covering and floor basement joint 3 and 2 sanitary seal, sealed enclosures, casing seal No. 4;
- Bougatfa Station: flooring of seals 3 and 4, painting the central hall.