lot-4-buildings-E-line

 

general-data-on-the-lot

  • Contract signature: 25/11/2010
  • OS start of work: 20/12/2010
  • Contract Completion: 04/12/2013
  • End of updated work taking account of the amendment: 01/28/2016
  • Contractual period updated: 1865 days
  • Contract Amount: 16 260 851.468 DT TTC

 

advancement-of-studies



The overall progress of studies and execution of the order of 94%.


Lot 4 : STATIONS TYPE % Avancement des études
ENNAJAH SS + RDC 95%
ETTAYARANE SS + RDC 90%
EZZOUHOUR SS + RDC 100%
HRAIRIA SS + RDC + 1 ET 87%
BOUGATFA SS + RDC + 1 ET 98%

progress-of-work



The overall physical progress is about 69%.


Lot 3 : STATIONS TYPE % Avancement des travaux
ENNAJAH SS + RDC 59%
ETTAYARANE SS + RDC 61%
EZZOUHOUR SS + RDC 66%
HRAIRIA SS + RDC + 1 ET 61%
BOUGATFA SS + RDC + 1 ET 82%

activities-of-the-past-month

  • Ennajah Station: Transplanting, metalwork, painting and plumbing;
  • Tayarane Station: slab formwork Shelters 1G and 1D, installation of wrought iron door, Hall traveler painting, plumbing;
  • Ezzouhour Station 2: Façade jackets Structured concrete coatings desk, iron door installation, plumbing works;
  • Hrairia Station: staircase cladding, coating basement, wall covering, coated in Shelter B ceiling, waterproofing, wood carpentry joined administration, wrought iron windows, sanitary wall coverings floor seal 2, elevator seal 4, poses frame staff , transplanting;
  • Bougatfa Station: Wall coverings basement, aluminum joinery, metalwork, decorative tube installation, Hall traveler paint, plaster ceilings Shelter, casing, plumbing.

forecast-Operations

  • Ennajah Station: casing basement administrative block painting, structured concrete;
  • Ettayarane Station: wrought iron, tile shelters 1G and 1D, painting;
  • Ezzouhour Station 2: Structured coatings for concrete facades, aluminum carpentry, Hall traveler painting;
  • Hrairia Station (O 2): Works fake ceiling, wall covering and floor basement joint 3 and 2 sanitary seal, sealed enclosures, casing seal No. 4;
  • Bougatfa Station: flooring of seals 3 and 4, painting the central hall.